Hi,
Sheet 1 - Contains following columns
- Resource Name
- Project Type
- Project Duration (Week Number)
Sheet 2 - Contains the following columns
- Project Type
- Project Duration (Week Number)
- % Allocation
% allocation is different for different combinations of Project Type and Project Duration (Week Number)
Ex. For Project Type A - % allocation is
- 15% if project duration is week 1
- 13% if project duration is Week 2
- 12% if project duration is week 3.
For Project Type B - % allocation is
- 25% if project duration is week 1
- 23% if project duration is Week 2
- 22% if project duration is week 3
For Project Type C - % allocation is
- 35% if project duration is week 1
- 33% if project duration is Week 2
- 32% if project duration is week 3.
I am trying to calculate % allocation for each project on 'Sheet 1' by referring to project type, project duration. It should return the appropriate % allocation value by referring to 'Sheet 2'
Please assist. Thank you!