Start time, end time in the project plan
Hi,
There are many situations where start date, end date and duration is not enough and one needs start time, end time as well. Does anybody know way to have
Start Time - 12/24 hrs
End time - 12/24 hrs
Duration - Days/Hours/Mins
The requirement is that end time should automatically populate the correct values by referring to the duration and predecessors.
Thanks in advance!
Answers
-
Hello Omkar,
I have done this in the past. The formulas can be dense but I think Mr. Paul has a lot of interesting insight in this issue.
Please see the link attached.
Good Luck!
Ward Hively,
Skyway Consulting Co.
https://community.smartsheet.com/discussion/68947/formulas-for-calculating-time
Ward Hively
President and Chief Consultant
🌉Skyway Consulting Co.🌉
Need Smartsheet Help? Schedule a complementary consultation click SCHEDULE
Does your Dashboard need a map that updates from Smartsheet Data? We pioneered 101+ ways to add a map to a Smartsheet Dashboard.
Smartsheet and GIS Integrations
✅ ArcGIS Online
✅ Arc Py
✅ Smartsheet Advanced
✅ Manage your GIS records from Dynamic View, Sheet or Report
✅ No Code (Limited Applications Apply)
Website: https://skywayconsultingco.com
LinkedIn: (49) Ward Hively | LinkedIn
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 351 Global Discussions
- 198 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 133 Brandfolder
- 127 Just for fun
- 127 Community Job Board
- 443 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 284 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!