IF / ISBLANK / NETWORKDAYS formula
I am trying to create a formula that will calculate the actual # of days a task had been open. I want to calculate from the task's "start date" to the current date IF the close out date column is empty/doesn't have a date. I attached a picture of what my sheet looks like. I have been messing around with formulas using IF, ISBLANK, and NETWORKDSAY, but haven't had any luck. Can someone suggest a formula that reflects the columns on my sheet?
Thank you!
Answers
-
@Gabriellenkv try this
=if([close-out date]@row="", networkdays([start date]@row, today()), networkdays([start date]@row,[close-out date]@row))
-
Thank you so much!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.9K Get Help
- 429 Global Discussions
- 147 Industry Talk
- 487 Announcements
- 5.2K Ideas & Feature Requests
- 86 Brandfolder
- 151 Just for fun
- 74 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!