Project schedule date formulas
Are you able to add a calculated date to a project schedule
So for example if the Project got approved June 5th then I would want the other tasks to start 1 day after then other tasks to start after that day and will take as long as 10 days to complete.
Are you able to add phases maybe that can be calculated?
Hope this makes sense
Answers
-
Hi Roshni,
It seems what you need is to set the Predecessor and Duration of the "other tasks". For details, refer to:
--Anson
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67K Get Help
- 441 Global Discussions
- 153 Industry Talk
- 501 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 79 Community Job Board
- 512 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 307 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!