Project Resource View
Comments
-
Jessica
By careful design you can have a range of ways to review your resources schedule.
In the sheet itself via the Red man, In Reports that summarise what each resource's tasks are in a list view, with the ability to interrogate via the Red man when that is helpful.
Or via the Home Button Resource View. Don't forget you can create filtered views for different teams.
You can even track your non human resources like a Training room as long as you can give it a "fake" email address.
So not sure what you are missing from this? If you need more, then we do offer a Free initial 1 hour consultation and can provide advice on Best Practice if needed?
Hope that helps
RichardR
Smarter Business Processes
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives