Project Resource View

Jessica Faris
edited 12/09/19 in Archived 2017 Posts

Hi:

I'm looking for a way to where the Project Resource View will list actual Task Names against each resource in my project sheet instead of the smartsheet file name against each person. . Is there a way the Project Resource View can be tailored and utilised as a resource management tool?

Comments

  • Richard Rymill SBP
    Richard Rymill SBP ✭✭✭✭✭✭

    Jessica

    By careful design you can have a range of ways to review your resources schedule. 

    In the sheet itself via the Red man, In Reports that summarise what each resource's tasks are in a list view, with the ability to interrogate via the Red man when that is helpful. 

    Or via the Home Button Resource View. Don't forget you can create filtered views for different teams. 

    You can even track your non human resources like a Training room as long as you can give it a "fake" email address. 

    So not sure what you are missing from this? If you need more, then we do offer a Free initial 1 hour consultation and can provide advice on Best Practice if needed? 

    Hope that helps

    RichardR 

    Smarter Business Processes