Status
anjaz
✭✭
Hello,
I would like to ask something about status. If I have parent and children – all status is 'in progress' or 'not started', and then I marked all children to 'complete', the parent also should be complete. How do I do this?
Thank you in advance,
Anja
Best Answer
-
Hi,
try the below formula in your parent status:
=IF(COUNTIFS(CHILDREN(), @cell <> "complete") = 0, "complete", "in progress")
Thank you!
Answers
-
Hi,
try the below formula in your parent status:
=IF(COUNTIFS(CHILDREN(), @cell <> "complete") = 0, "complete", "in progress")
Thank you!
-
Thank you.