Percentage complete calculation
System
Employee
This discussion was created from comments split from: Looking to add a percentage complete calculation.
Answers
-
Hello I'm using The PMO Template. I'm working in the project plan sheet. The % complete are no longer calculating for the summary value. I'm not sure if I inadvertently deleted the formula, but I'm not sure how to get it back for each milestone. I need it so the schedule delta is functioning appropriately. Please help
-
Hello,
I think you should use "increase indent" on line 8.
If you look, line 8 is at the same level as line 2 "planning".
If this is the reason, please let us know
Thank you
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.5K Get Help
- 448 Global Discussions
- 145 Industry Talk
- 481 Announcements
- 5.1K Ideas & Feature Requests
- 85 Brandfolder
- 152 Just for fun
- 73 Community Job Board
- 492 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 304 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!