% Schedule Complete Calculation
I am using a formula to calculate the % schedule complete based on project start and end date.
=(NETWORKDAYS([Start Date]1, TODAY(), Holidays2:Holidays10)) / (NETWORKDAYS([Start Date]1, [End Date]1, Holidays2:Holidays10))
Is there a way to get this formula to just return 100% if the % complete is above 100%?
Answers
-
Try this:
=IF((NETWORKDAYS([Start Date]1, TODAY(), Holidays2:Holidays10)) / (NETWORKDAYS([Start Date]1, [End Date]1, Holidays2:Holidays10)) > 1, 1, (NETWORKDAYS([Start Date]1, TODAY(), Holidays2:Holidays10)) / (NETWORKDAYS([Start Date]1, [End Date]1, Holidays2:Holidays10)))
-
I would use the IF syntax.
"=IF( Your Formula >= 1, 1, Your Formula)"
=IF((NETWORKDAYS([Start Date]1, TODAY(), Holidays2:Holidays10)) / (NETWORKDAYS([Start Date]1, [End Date]1, Holidays2:Holidays10))>=1,1,(NETWORKDAYS([Start Date]1, TODAY(), Holidays2:Holidays10)) / (NETWORKDAYS([Start Date]1, [End Date]1, Holidays2:Holidays10)))
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!