As usual with SmartSheets, I don't think I'm too far off with this one, but I've hit a snag.
I've managed to get the Harvey Balls working properly for what I'd like on their own rows, but I'm trying to bring an extra function into play for Project Health.
I'd like to mark Projects in Blue for Completed. That seemed easy enough, but now I've been tasked with marking any uncomplete according to Date Slip.
Anything still < End Date to be Green, less than 14 days overdue to be Yellow, and over that to be Red.
Do I merely have the dates and status the wrong way round in the formula, and\or should Blue come first?
=IF([% Complete]34 < 1, "Green", IF(AND([End Date]34 <TODAY +14))[% Complete]34 < 1, "Yellow", IF((AND[End Date]34 >TODAY +14))[% Complete]34 < 0.99, "Red", IF([% Complete]34 = 1, "Blue"))))
btw, Row 34 is my overriding Project status
Thanks all, and I hope our US based S³ community enjoy Thanskgiving.