How do I get my sheet to flag automatically
Here is what I'm trying to do:
If planned start is in the past and start date is blank...I need late start column to populate a red flag
Any idea on this? Is it a workflow or a formula that is needed?
Best Answer
-
Try this formula =IF(AND(ISBLANK([Start Date]@row), [Planned Start Date]@row < TODAY()), 1, 0)
MARLANA KALINOWSKI
Sr. Business Analysts / Smartsheet Solutions
National Pharmacy Services | Genoa Healthcare
Answers
-
Try this formula =IF(AND(ISBLANK([Start Date]@row), [Planned Start Date]@row < TODAY()), 1, 0)
MARLANA KALINOWSKI
Sr. Business Analysts / Smartsheet Solutions
National Pharmacy Services | Genoa Healthcare
-
Thank you!!!! How can the flag disappear when the status column says "completed?
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!