Formula Date
Shimy
✭✭
Am I able to create a date 4 weeks prior to a specific date through a formula? So, every entered PM Requested Ship Date would auto generate a Required process completion Date... Do I use =DATE( OR =IF( Thanks!
Best Answer
-
Should just be able to use a basic subtraction in the Required process completion Date column.
=[PM Requested Ship Date]@row - 28
Cheers,
John
Answers
-
Should just be able to use a basic subtraction in the Required process completion Date column.
=[PM Requested Ship Date]@row - 28
Cheers,
John
-
You are awesome. I was making it way more complicated for no reason. Thank you!
-
No problem. Overcomplication is coding is easy to do. Sometimes easy is right. 😂
-
Amen to that!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 379 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 302 Events
- 33 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!