Am I able to create a date 4 weeks prior to a specific date through a formula? So, every entered PM Requested Ship Date would auto generate a Required process completion Date... Do I use =DATE( OR =IF( Thanks!
Best Answer
-
Should just be able to use a basic subtraction in the Required process completion Date column.
=[PM Requested Ship Date]@row - 28
Cheers,
John
Answers
-
Should just be able to use a basic subtraction in the Required process completion Date column.
=[PM Requested Ship Date]@row - 28
Cheers,
John
-
You are awesome. I was making it way more complicated for no reason. Thank you!
-
No problem. Overcomplication is coding is easy to do. Sometimes easy is right. π
-
Amen to that!