Hi everyone,
Newer Smartsheet user here! 😊
I am setting up sheets to capture ongoing project status updates from team members.
I have a (dropdown)column that shows QI Phase and a blank column that shows % complete.
Ask: I am trying to figure out how to write a formula that will reflect a % complete based on what phase a project is in.
If the project is in the "Initiate Project" or "Assess the Current State" then I want the percent complete to show less than 25%.
If the project is in the "Design the Future State" or "Test and Implement" phase then I want the percent complete to show 25-50%.
If the project is in the "Sustain" or "Spread" phase then I want the percent complete to show 50 to 75%.
If the project is in the "Completed: Transferred to Operations" phase then I want it to show 100% complete.
Any guidance would be super appreciated!!!
Sade