Help! Expected Progress Formula #INVALID OPERATION
My project health column is based on Expected Progress column. Works great with the exception where there there's no data (blank cell) the formula returns #INVALID OPERATION
I've tried adding a IF(OR(ISBLANK but haven't been able to get it correct. Would appreciate help/guidance!. Thank you
=IF([% Complete]@row = 1, "Blue", IF(OR(([Expected Progress]@row - [% Complete]@row) < 0.1, [% Complete]@row >= [Expected Progress]@row), "Green", IF(AND(([Expected Progress]@row - [% Complete]@row) >= 0.1, ([Expected Progress]@row - [% Complete]@row) <= 0.25), "Yellow", IF(([Expected Progress]@row - [% Complete]@row) > 0.25, "Red", ""))))
Answers
-
Hello @AClark200,
How would you like to handle the situations where the Expected Progress cell is blank? Would you like the formula to return a blank (e.g., "") as well? If so, would the following work?
=IF([% Complete]@row = 1, "Blue", IF(ISBLANK([Expected Progress]@row]), "", IF(OR(([Expected Progress]@row - [% Complete]@row) < 0.1, [% Complete]@row >= [Expected Progress]@row), "Green", IF(AND(([Expected Progress]@row - [% Complete]@row) >= 0.1, ([Expected Progress]@row - [% Complete]@row) <= 0.25), "Yellow", IF(([Expected Progress]@row - [% Complete]@row) > 0.25, "Red", "")))))
Hope this helps and that you have a great day,
Jason Albrecht MBA, MBus(AppFin), DipFinMgt
LinkedIn profile - Open to work
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!