Hello all and thanks for your help in advance!
I am working on building project plan templates, dashboards, and reports for my PMO.
As EV is not a part of the request, I need to focus solely on schedule.
Here is what I am looking to do and need advice on how to formulate...
A task has an Actual Start Date of 02/01/24 and a duration of 20 days, it should be 90% complete by EOD 02/26/24 (02/19/24 is non-working holiday). So 100% / 20 Days = 5% completion per day.
How do I build a formula to show what completion percentage we should be based on current date?