Formula Help
Hi,
I am trying to find a formula that finds the closest project board date following a milestone date. From the screen shot below I want to look at the dates in the second column and find the next board date from the cell highlighted in the finish column. Is there a way smartsheet can do this or will I have to do it manually?
Best Answer
-
Try:
=MIN(COLLECT([Project Board Dates]:[Project Board Dates], [Project Board Dates]:[Project Board Dates], @cell> Finish Date]@row))
Answers
-
Try:
=MIN(COLLECT([Project Board Dates]:[Project Board Dates], [Project Board Dates]:[Project Board Dates], @cell> Finish Date]@row))
-
That works! Thank you so much
-
Happy to help. 👍️
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!