Hi all,
Trying to solve a quite simple problem with some most of the work already done.
I'm trying to show in a dashboard the percentage of tasks which should have been completed based on planned finish, vs the actual tasks completed.
I have a "Planned Finish" column, a "Status" and "Actual Completion Date" column. I intend to use a formula in sheet summary which I can then report on in the dashboard.
My assumption is this will be involve a combination of COUNTIF, TODAY and division, but I can't get my head round it.
Any help appreciated. Thanks