Hey There,
I work for a construction company, and one of our subdivisions has multiple townhome blocks. We are currently building 3 blocks, but don't know when we will start the other ones (all dependent on sales)
I'm wondering if there is a way to get the % Complete for the whole project, not just the blocks currently in progress. When I use the built in function, it only calculates the % Complete base on the 3 blocks we are building, because the remaining 12 blocks don't have start and end dates.
I know the simple solution would be to sum the % Completes and divide by the number of items, but that would not be accurate as some blocks are a different design, and therefore require more time.