I'm facing a challenge.
I've got a schedule with Start & End Date, when new lines are added I usually go and manually copy the Start & End Date to the Target Start & Target End Date on the same sheet. Initially I can add a formula to copy that date across however what I don't want is for the Target Start and Target End date to also change when the user updates the Start & End Date coz that need to be the "Baseline" for the schedule.
I already looked at the Community similar issues and appreciate the option is available to copy row to another sheet and use "Vlookup" however, to do that requires additional effort.
Just wanted to know if there is a alternative fix?
Should you need further information let me know. Would really appreciate some assistance.
Thank you.