What is wrong with my formula? I want to calculate 3 workdays from the survey request date but only if the site plan test fit is checked…
Best Answers
-
Move that very first closing parenthesis after the 1 to the end of the formula. You will also need to replace that first comma with an =.
-
@holli.nunn Instead of "= 1" you would have "= "Yes"".
Answers
-
Move that very first closing parenthesis after the 1 to the end of the formula. You will also need to replace that first comma with an =.
-
Thank you @Paul Newcome ! That challenged my reading comprehension and totally worked :)
-
@Paul Newcome - I had to switch this column for a colleague to a drop down list… how do I adjust this to pull over the 'yes'?
-
@holli.nunn Instead of "= 1" you would have "= "Yes"".
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 444 Global Discussions
- 142 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 83 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 489 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!