What is wrong with my formula? I want to calculate 3 workdays from the survey request date but only if the site plan test fit is checked…
Best Answers
-
Move that very first closing parenthesis after the 1 to the end of the formula. You will also need to replace that first comma with an =.
-
@holli.nunn Instead of "= 1" you would have "= "Yes"".
Answers
-
Move that very first closing parenthesis after the 1 to the end of the formula. You will also need to replace that first comma with an =.
-
Thank you @Paul Newcome ! That challenged my reading comprehension and totally worked :)
-
@Paul Newcome - I had to switch this column for a colleague to a drop down list… how do I adjust this to pull over the 'yes'?
-
@holli.nunn Instead of "= 1" you would have "= "Yes"".
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!