What formula do I use
Mdonan
✭
For "When start date is populated, auto turn Status to ‘in progress’
Im new to Smartsheet and ProDesk appointments are not available until June 2nd. Any guidance is appreciated, thank you!
Answers
-
You should get what you need if you put that in your status column and make it a column formula
=IF(ISBLANK([Start Date]@row), "Not Started", "In Progress")
-
-
It might be to basic of a solution but assuming your statuses are, Not Started, In Progress and Completed, I would maybe try something like:
=IF([Target End Date]@row ="", "Completed", IF([Target Start Date]@row ="", "Not Started", IF([Target Start Date]@row <>"", "In Progress")))
This might need some maniputlation, but I think it all looks right!
Good luck!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 379 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 302 Events
- 33 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!