Gant chart progress bar

Why does the progress bar in the gant chart WP3 and WP5 say that you are ahead of schedule even though you are not ? There are no dependencies on the activities. They are all independent.
All the activities under are on time but the sum up is ahead of schedule.
These activities are progressig according to the timeline.
Answers
-
The progress bar is just a visual representation of the % complete column, that's it.
-
So how does it calculate the % complete from the activities then and is there something we can do to change it ?
-
Hi,
I hope you're well and safe!
Unfortunately, as far as I know, it's not possible now except for changing dependencies, working days, and similar, but it's an excellentΒ idea!
PleaseΒ submit this asΒ a Product Feedback or Idea (If it hasn't been added already) when you have a moment.
I hope that helps!
Be safe, and have a fantastic week!
Best,
AndrΓ©e StarΓ₯ | Workflow Consultant / CEO @ WORK BOLD
β Did my comment(s) help/answer your question or solve your problem? Please support the Community and me byΒ marking it - Insightful π‘- Vote Up β¬οΈ - Aweseome β€οΈ - or/and as the accepted answer. It will make it easier for others to find a solution or help to answer! I appreciate it, thanks!SMARTSHEET EXPERT CONSULTANT & PARTNER
AndrΓ©e StarΓ₯ | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E: andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.8K Get Help
- 474 Global Discussions
- 205 Use Cases
- 517 Announcements
- 5.5K Ideas & Feature Requests
- 87 Brandfolder
- 157 Just for fun
- 83 Community Job Board
- 521 Show & Tell
- 36 Member Spotlight
- 3 SmartStories
- 309 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!