Gant chart progress bar
Why does the progress bar in the gant chart WP3 and WP5 say that you are ahead of schedule even though you are not ? There are no dependencies on the activities. They are all independent.
All the activities under are on time but the sum up is ahead of schedule.
These activities are progressig according to the timeline.
Answers
-
The progress bar is just a visual representation of the % complete column, that's it.
-
So how does it calculate the % complete from the activities then and is there something we can do to change it ?
-
Hi,
I hope you're well and safe!
Unfortunately, as far as I know, it's not possible now except for changing dependencies, working days, and similar, but it's an excellent idea!
Please submit this as a Product Feedback or Idea (If it hasn't been added already) when you have a moment.
I hope that helps!
Be safe, and have a fantastic week!
Best,
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
✅ Did my comment(s) help/answer your question or solve your problem? Please support the Community and me by marking it - Insightful 💡- Vote Up ⬆️ - Aweseome ❤️ - or/and as the accepted answer. It will make it easier for others to find a solution or help to answer! I appreciate it, thanks!SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.4K Get Help
- 424 Global Discussions
- 221 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 145 Just for fun
- 62 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!