I have a sheet with a restricted column called "Completion Date". The unrestricted column is called "Status" and users can change using a drop down to "Done". Is it possible to have the "Completion Date" column filled by the system based on when the user updated the "Status" column to "Done"?
Thanks!
Best Answer
-
Yes, you can create an automation to record a date in the "Completion Date" column when the "Status" column value changes to "Done".
Answers
-
Yes, you can create an automation to record a date in the "Completion Date" column when the "Status" column value changes to "Done".
-
Thanks!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.3K Get Help
- 462 Global Discussions
- 156 Industry Talk
- 506 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 517 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!