Hi
I am using a column with dropdown information which is equivalent to a bucket…I am using the word "Deliverable"
When I add a subtask which are a component of that task (indented tasks in the grid view), they don't inherit the Deliverable that is allocated to the top level task.
I then have to go back to the grid view and add them manually.
Why don't subtasks inherit information when if as a project they roll up to the start and finish dates and % complete if set?
I now have to think about formulas and workarounds for this. In products like planner and project online, any subtasks are linked to the main item. Any tasks in project that are indented tasks do get the "bucket" that they are in.
I am going to put a feature request in additional fields that have roll up features.
If anyone has this experience it would be good to know
Thanks
Purnima