How can I visualise resources capacity in Resource Management from only one Sheet?

I enabled Resource Management in Smartsheet and I wanted to test the functionality with a Copy of my initial plan.

Once I validated that the tool was working I deleted the "Copy of VayScale" sheet and enabled Resource management in the original Sheet.

Unfortunately when I checked the "Copy of VayScale" is still taken into account and I cannot remove it.

Note:

  • The "Copy of VayScale" sheet is fully deleted

Is there any way I can only take into account 1 Sheet?

Can I filter out other Sheets?

Thanks!

Answers

  • Brian_Richardson
    Brian_Richardson Overachievers Alumni

    You can filter the Projects on the Schedule tab by using the left side menu. However, it sounds like you want that project to go away permanently, so in that case open the project's page (search for project name and click on it, or click Projects and find it), then click Edit Project Profile, then scroll to the bottom and Archive the project.

    When you Archive, it will disappear from all reporting.

    BRIAN RICHARDSON | PMO TOOLS AND RESOURCES | HE|HIM