Subtract weeks for lead time with notifications
I'm trying to subtract 6 weeks from my Factory Shipment Date (row 1) to give me lead time to notify Port Authority which is assigned to someone on my team. I have 15 categories/columns like this with 4 team members. The categories need a lead time of 6 weeks, 4 weeks, 3 weeks, 2 weeks, 1 week or 3 days. This is for a huge project, trying to deliver 100 modular homes into NYC.
Comments
-
If I'm understanding correctly, could you use something like this
=[Factory Ship Date]1 - [Lead Time (Weeks)]1 * 7
Then under notifications, use that column to email "Team Member" the reminder? For 3 days, your lead time weeks would have to be .5, I don't know another way around that.
Jason Tarpinian - Sevan Technology
Smartsheet Aligned Partner
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives