Reverse PMO query
Hi there,
I am running hotel opening projects - and using the PMO set up to run multiple openings simultaneously. Now, the one driver that changes the tasks (+700) is the "practical completion date" of the building. I just want to input the delivery date and that all tasks dates changes - in the current PMO set up the driver is the "start date" of the project, and I need to base timelines on the "end date" of the project. Does anyone has the answer for me please?
I sincerely appreciate your feedback on support in this community.
Regards,
Rinse
Answers
-
Hi you can leverage Start-to-Finish predecessors to reverse engineer from an end date.
See my screenshot as an example. The first set is a normal waterfall, cascading with Finish-to-Start dependencies down to an end date that's driven by the tasks above it. Each task is dependent on the task before it in time.
The second set is a reversed waterfall, cascading upwards and backwards in time from the End Date using Start-to-Finish dependencies. Each task is Start-to-Finish dependent upon the task after it in time.
You will probably have to do a lot of heavy lifting to reverse engineer the dependencies for 700 tasks. However, this is the only method I know of, since you cannot use formulas in the Start/Finish fields in Smartsheet when dependencies are enabled.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!