I created a report to show baseline variance metrics for all projects in our portfolio. In the report, I tried to summarize the project variance field, and you can see the result below. I do not get the expected results using either average or sum.
Is it because the project variance field display in the format xxd rather than xx (e.g. 15d vs 15). And if so, does the baseline variance field exist anywhere without the “d” or do I need to parse the field or find a different way?
As always, thank you in advance!!!