Anybody used Workday function? It adjusts the date skipping holidays and weekend but I am observing a weird behavior-> it works absolutely perfect for current year but disregards next year's weekend and holiday. Tried two approaches but same result 1) Entered holidays in project settings 2) Creating a holiday column
First column is duration and second is finish date derived through a calculated formula using workday: Finish date of previous entry + duration
7w | 10/29/24 |
|---|
3w | 09/18/24 |
12w | 12/12/24 |
9w | 01/24/25 |
last entry is wrong: 12/12/24+ 9w or 45 days = 01/24/25 exact 45 days after 12/12/24 though it should be sometime in feb skipping 9week*2 days (weekend)
rest entries are working fine. I have included holidays too so might be difference of 1-2 days if you calculate at your end. But last entry is absolutely wrong.