Struggling with Dependencies and Lead Time Calculations - What Are Helper Columns?
System
Employee
This discussion was created from comments split from: Formulas in Columns with Dependencies?.
Answers
-
I read a lot about Helper columns. What are these? I want formulas in my Start date, but as soon as I enable dependencies it breaks.
I am also trying to create a lead time based on due date - creation date but unable to get this to work as well.
-
A helper column is simply a column that you insert into your sheet to help functionality usually through formulas.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.1K Get Help
- 349 Global Discussions
- 199 Industry Talk
- 427 Announcements
- 4.4K Ideas & Feature Requests
- 133 Brandfolder
- 127 Just for fun
- 127 Community Job Board
- 455 Show & Tell
- 28 Member Spotlight
- 1 SmartStories
- 282 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!