How do I add a Task column to my Dashbaord
Hi There
I currently have a dashboard setup and want to add a widget that gives me the number of tasks at each stage from my Task Status column. The problem is when i go to find this through "Select Data" in the "Sheet summary view" the Task status column and its values are not shown.
Why is this how do I get to see them to select them?
Thanks for anyone's help on this
Answers
-
You need to select the +New Field at bottom of sheet summary to add the summary field. Give it the name you want to use and enter a formula e.g. =SUMIF([Project Status]:[Project Status], "Budget", Total:Total)
Then when adding the widget from the summary sheet, the fields you entered will show up.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.2K Get Help
- 445 Global Discussions
- 143 Industry Talk
- 476 Announcements
- 5K Ideas & Feature Requests
- 84 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!