project date 6 weeks from another date on a row
How do I write a formula to project out 6 weeks from another date on that row?
Answers
-
You can just add days to the source dates.
=[Date Column]@row +42 would add 6 weeks
-
Doesn't work
-
Ok, now I have it, thanks. Also, how do I do that as a column function
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 59 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!