Sum(IF(ISDATE
Options

Robert S Fike
✭✭✭✭
Can this statement work. Getting a syntax issue.
=IF(ISDATE([Plans To Field Date]@row]@row), Sum(IF(ISdate([Slab Inspection]@row), 1, 0), IF(ISDATE([Frame Inspection Date]@row), 1, 0), IF(ISDATE([Cabinet Install Date]@row), 1, 0), IF(ISDATE([Final C.O. Date]@row, 1, 0) + 7)), SUM(IF(ISDATE([Spec Release Date]@row), 1, 0), IF(ISDATE([Selections Completed Date]@row), 1, 0), IF(ISDATE([Final Plans & Specs Done Date]@row), 1, 0), IF(ISDATE([Budgets & PO's Done Date]@row), 1, 0) + 2)
Best Answer
-
=IF(
ISDATE([Plans To Field Date]@row),
SUM(
IF(ISDATE([Slab Inspection]@row), 1, 0),
IF(ISDATE([Frame Inspection Date]@row), 1, 0),
IF(ISDATE([Cabinet Install Date]@row), 1, 0),
IF(ISDATE([Final C.O. Date]@row), 1, 0)
) + 7,
SUM(
IF(ISDATE([Spec Release Date]@row), 1, 0),
IF(ISDATE([Selections Completed Date]@row), 1, 0),
IF(ISDATE([Final Plans & Specs Done Date]@row), 1, 0),
IF(ISDATE([Budgets & PO's Done Date]@row), 1, 0)) + 2
Answers
-
=IF(
ISDATE([Plans To Field Date]@row),
SUM(
IF(ISDATE([Slab Inspection]@row), 1, 0),
IF(ISDATE([Frame Inspection Date]@row), 1, 0),
IF(ISDATE([Cabinet Install Date]@row), 1, 0),
IF(ISDATE([Final C.O. Date]@row), 1, 0)
) + 7,
SUM(
IF(ISDATE([Spec Release Date]@row), 1, 0),
IF(ISDATE([Selections Completed Date]@row), 1, 0),
IF(ISDATE([Final Plans & Specs Done Date]@row), 1, 0),
IF(ISDATE([Budgets & PO's Done Date]@row), 1, 0)) + 2
-
TYVM
-
Happy to help!😁
Help Article Resources
Categories
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!