What I'm looking to do is create a finish-to-finish dependency where the end date is extended but not the duration for a given task. This way a task can start immediatly but it may finish later than the duration. This way the duration of the task can outgrow the FF dependency but never be less than the FF dependency end date. For example, I'm looking for this:
Smartsheets currently will backdate the start for tasks with a FF dependency like this:
I'm assuming this can be changed by a project setting but I can't seem to find it.