Please help to calculate the % Planed in Summary row.
Thanks in advance
-
Hi @Md Ariful Islam,
Your formula looks correct to me:
=AVG(CHILDREN())
Is it not behaving the way that you want?
Nathan Braun (Founder of SSFeatures) (nathan@ssfeatures.com)
SSFeatures - The browser extension that adds essential features into Smartsheet.
-
@Md Ariful Islam Are you getting an error or an unexpected output? How exactly are the child rows being populated?
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.9K Get Help
- 441 Global Discussions
- 153 Industry Talk
- 501 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 79 Community Job Board
- 511 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!