Calculate % Planned in parent row
System
Employee
This discussion was created from comments split from: Calculating Actual Progress vs Planned Progress base on Today's Month & Year.
Answers
-
Please help to calculate the % Planed in Summary row.
Thanks in advance
-
Hi @Md Ariful Islam,
Your formula looks correct to me:
=AVG(CHILDREN())
Is it not behaving the way that you want?
SSFeatures - The browser extension that adds more features into SmartSheet.
- Automatic sorting, sorting with filters, saving sort settings
- Spell checking
- Report PDF generator that supports grouped and summarized reports
-
@Md Ariful Islam Are you getting an error or an unexpected output? How exactly are the child rows being populated?
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 219 Industry Talk
- 457 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!