Smartsheet Hierarchy % Complete Formula
Smartsheet Community:
Does Anyone Have The Formula That Smartsheet Use to Calculate % Complete When Dependencies is Enabled in Project Settings?
I Would Like to Use That Formula for % Complete Plan As a KPI For Project Progress.
Thanks
Answers
-
Hi @Champ
What the formula does is basically % complete times the duration for the task over the duration in the parent row, which is the total duration of all children.
So, it will be something like =([% Complete]@row*Duration@row)/[Duration]x), where x is the row# of the parent
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!