Smartsheet Hierarchy % Complete Formula

Champ
✭✭✭
Smartsheet Community:
Does Anyone Have The Formula That Smartsheet Use to Calculate % Complete When Dependencies is Enabled in Project Settings?
I Would Like to Use That Formula for % Complete Plan As a KPI For Project Progress.
Thanks
Answers
-
Hi @Champ
What the formula does is basically % complete times the duration for the task over the duration in the parent row, which is the total duration of all children.
So, it will be something like =([% Complete]@row*Duration@row)/[Duration]x), where x is the row# of the parent
Thanks,
Aravind GP| Delivery Manager
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com