Smartsheet Hierarchy % Complete Formula

Smartsheet Community:

Does Anyone Have The Formula That Smartsheet Use to Calculate % Complete When Dependencies is Enabled in Project Settings?

I Would Like to Use That Formula for % Complete Plan As a KPI For Project Progress.

Thanks

Answers

  • AravindGP
    AravindGP ✭✭✭✭✭✭

    Hi @Champ

    What the formula does is basically % complete times the duration for the task over the duration in the parent row, which is the total duration of all children.

    So, it will be something like =([% Complete]@row*Duration@row)/[Duration]x), where x is the row# of the parent

    Thanks,

    Aravind GP| Principal Consultant

    Atturra Data & Integration

    M: +61493337445

    E:Aravind.GP@atturra.com

    W: www.atturra.com

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!