I need to have a column calculate the status of a project based on where today stands compared to its % complete and where we are between the projected start and finish date.
As an example. This is what is entered manually.
Start End % complete Project status
01/07/24 22/11/24 92% In Progress - On Track
Today is Oct 18th and the %complete is 92% I would say that the project status is correct and should remain as In Progress - On Track.
But if today was November 25th and the % complete is less than 100% the project status should be In Progress - Delayed
The other project status options are ”Not started” and “Closed”