I'm looking for help with tracking and reporting on tasks that are interdependent across multiple projects.
Background:
We are running a Program Office that includes 8 strategic workstreams plus a BAU stream. There are a number of tasks/activities that have cross project dependencies. For example, a monthly board meeting which is a BAU activity is relevant to any workstream that needs to provide an update to the board in that month. In other examples, there are outputs from one workstream that are an input to another.
Each workstream has a project dashboard and the program also has a strategic program dashboard.
What we already know how to do and understand:
- We know how to link rows from one sheet to another
- We know how to turn on the highlighting feature so that we can easily see changes that have occurred.
- We understand how to set predecessors so that the activities are directly linked to each other
- I've just read on another post that we can set an alert/notification for when these activities are changed, so that's really helpful and will investigate that further as well.
Our specific questions that we don't know the answer to:
- Is there a way to do conditional formatting or somehow visually highlight these rows that are linked from another sheet? We would like each project manager to be able to quickly and easily see where they have an activity that links out to something else, or where they have an activity that links in from something else.
- Is there a way to show this visually on the gant chart, that there is activity from another stream that this project is dependent upon, or that another stream is dependent upon this activity?
- Is there a way to create a report that shows just these interdependent tasks. We'd like to include this report on the project and program dashboard.
Thanks in advance.
Katie.