Baselining

Hi All, can you add baseline dates for added tasks after a sheet has been initially Baselined?

Best Answer

  • Michelle Choate 2
    Michelle Choate 2 ✭✭✭✭✭✭
    Answer ✓

    You will have to either (a) re-baseline your sheet, or (b) manually add these dates into your baseline columns.

    Michelle Choate

    michelle.choate@outlook.com