Baselining
Hi All, can you add baseline dates for added tasks after a sheet has been initially Baselined?
Best Answer
-
You will have to either (a) re-baseline your sheet, or (b) manually add these dates into your baseline columns.
Michelle Choate
michelle.choate@outlook.com
Always happy to walk through any project you need help with! Book time with me here: https://calendly.com/michelle-choate
Answers
-
You will have to either (a) re-baseline your sheet, or (b) manually add these dates into your baseline columns.
Michelle Choate
michelle.choate@outlook.com
Always happy to walk through any project you need help with! Book time with me here: https://calendly.com/michelle-choate