Hello all. I am having an issue, and it may be a very disappointing deal-killer.
I am a national program manager and have taken on one of our organization's largest programs. I am attempting to evaluate smartsheets as a potential MS Project replacement.
Issue
In Project 1 (P1), I create a link to a task in Project 2 (P2). In P1, I can see the small blue link-reference, but the text of the cells remains blank.
Steps
- I have imported 3 relatively small .mpps.
- I have created a simple, small test roll-up project
- In P1, I select only the task name, create the link to P2, highlighting only the task name in P2
- In P1, the task name remains blank. There have been times when I leave and come back, the value populates. Sometimes not. In other instances, I have deleted the reference, left, and when I returned, the value is populated but the link is gone.
- If I perform this process highlighting multiple fields in P1, then highlighting the same fields in P2, I achieve similar results.
Reasoning for the need
Effective cell linking will allow me to provide me and senior leadership with a simple holistic view of what is happening within the program, allowing us to quickly identify workstream, market, and program-wide critical paths, identify issues, communicate timelines, etc.
Impact of the issue
This issue has the potential of preventing smartsheet from being an effective replacement for the organization.
If the creation of a link to another smartsheet brings back blank results, I don't know how the tool is usable - I feel like I must be missing something. I am seeing this issue reported in the forums for years with only rudimentary workarounds. I don't see these workarounds as being feasible for an enterprise solution. I have high hopes for SmartSheets and would really appreciate some assistance.
Thanks!
Pete