End Date - Move End date on current task if task isn't complete

Hi I would like to have the fuctionality to see what the projected date of completion is going to be on my project based on the outstanding tasks. Currently when a end date is reached it doesn't move on so doesn't move the dependancies which means the overall project plan stays at the original baseline. The only way to move it on is by updating the End Dates for the tasks that are not complete.
Can you please advise if there is a way to acheive auto-moving a project on based on completion status?
Many thanks,
Mike
Answers
-
Hey @Michael Foster , do you already have a baseline on your project? Or do you use manual baselining? Also, you could use an automation to continue to move the dates forward based on a condition, which will then move the anything that is dependent on it forward and show you the variance from the baseline columns.
If you want to walk through creating the automation, my calendar link is in my signature :) Happy to help on zoom!
Michelle Choate
michelle.choate@outlook.com
Always happy to walk through any project you need help with! Book time with me here: https://calendly.com/michelle-choate
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.2K Get Help
- 452 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!