Calculate duration basing on resource allocation
Answers
-
This is expected behaviour - when you activate dependencies on a sheet, you can't use formulas in the Start Date, End Date, Duration, % Complete, and Predecessors columns. Take a look here for more information on dependencies: Activate dependencies and use predecessors in sheets.
You could either keep dependencies disabled to use your own formulas in the Duration and End Date columns, or you could add another Duration column and another End Date column to the sheet so that you can use formulas in those columns, as they won’t be the ones used in the project settings.
Hope that helps!
Georgie
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.2K Get Help
- 451 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!