Problem: Resource Management rounds all task durations to full days during sync, regardless of partial-day durations (e.g., 1.25 days) defined in Smartsheet project plans. This leads to inaccurate resource allocations, especially over-allocation (e.g., 200% allocation for same-day tasks).
Request: Recognise partial-day durations when syncing, rather than rounding up to full days and accurately assign allocation