Granular detail for Project Plan

Randy Van Winkle
Randy Van Winkle โœญโœญโœญโœญ
edited 05/12/25 in Formulas and Functions

Hello, I am being asked to up the level of accountability on completion on my Project Plans. I would like to get a date stamp on the day that each line item (specifically header rows) reaches 100%. Additionally, I would like to record the "% Done" at the end of the day specified as the "End Date" of the task. I tried to accomplish this through Automations.

Record 100% Date

  • Trigger - when rows are added or changed; when % Done changes to 100%
  • Condition - Task Name - is not blank
  • Record a date - record a date in "Completion Date"
  • Not doing anything when testing

Record % Done on End Date

  • Tried to set up as Change Value in a Cell, but not sure how to use the current value in % Done column to stamp in "% on End Date" column. Seems to only accept specified value

Maybe there is a way to set this up via column formula?