Hi everyone,
I’m migrating a schedule from MS Project to Smartsheet and I noticed a difference in how FS (Finish-to-Start) dependencies behave. In MS Project, when a task has an FS predecessor, the successor’s start date is set to the same day the predecessor ends. But in Smartsheet, the successor is pushed to start one day later instead. Is there a way to configure Smartsheet so that FS dependencies start on the same date as the predecessor’s finish date?
Anybody could share any tips and tricks?