Hi all,
Weird problem I am facing today and wondering if something has changed. I have run global updates in the past to push new reports out to active projects (its very nuanced with having to update the report for each project individually) but anyways…
Today I tried to run one and the test example worked fine with updating the new source sheet to the new report but when I commit the change - I am thrown an error "failed to copy report"
My source mapping is green though from the passed test sheet
Any ideas?
The report is nested in a different folder from the sheet but again, that has not been a problem in the past