In my job as a scheduler a common question is "which of the predecessors for this activity is driving the date?" Currently I have to rely on my own knowledge of my schedules or, worst case, I have to look at every predecessor until I find the one I am looking for. Microsoft Project is nice because it has the "inspect" tool. P6 is nice because it has the "driving" column in the activity details.
I would like a column that displays, ideally, the line number and name of the driving predecessor for each activity. If that's not possible, just the name or line number is fine. If this is not possible at all, I would just like to know if there's any way at all to find the driving predecessor quickly in Smartsheets.
So in short, my question is this- when you are asked what the driving predecessor for a task is, how do you find the answer?