Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Start No Earlier Than
Looking for a way to add a "Start No Earlier Than" clause into a sheet? We want to link Task B to its predecessor, Task A, but also indicate that Task B must start no earlier than a certain date. This way if we modify dates/durations for Task A, it modifies Task B while still noting the earliest start date. Any help?
Tags:
Comments
-
Hi Kelci,
Task B needs a second predecessor, call it Task C. Make Task C a milestone on the "Start No Later Than" date.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives