Start No Earlier Than
Looking for a way to add a "Start No Earlier Than" clause into a sheet? We want to link Task B to its predecessor, Task A, but also indicate that Task B must start no earlier than a certain date. This way if we modify dates/durations for Task A, it modifies Task B while still noting the earliest start date. Any help?
Tags:
Comments
-
Hi Kelci,
Task B needs a second predecessor, call it Task C. Make Task C a milestone on the "Start No Later Than" date.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives