Hi guys, any advise on how works with % completed vs planned % completed as smartsheets only has column for % completed?, has anyone achieved to make a similar column for planned %?
Hello,
You can create a new text/number column in your sheet and format it for percent. Details on formatting columns for percent can be found in our Formatting Options help article.
If you need planned percent complete to be calculated for you, you'll need to create a formula in Smartsheet that does this. You can find the complete list of functions here: https://help.smartsheet.com/functions
I have a form that will be filled out internally. There's a cell labeled "Department" which contains 8 dropdown list values. There's a another cell called "Executives" which are the leaders of these departments. In the form, I'm attempting to do a logic where when you choose a specific "Department", then the cell…
I shared access to a user to a specific folder under workspace A (folder is 2025-09-Service Factory). However, I can see that he's shown to have access to all the other child folders under 02-ACTIVE Initiatives. Why is that when I only shared out one folder? Is there a way to only share access to users to ONLY specific…
what i can do if all my existing smartsheet gant files can't be open after change my plan to Pro? what could be the reason ?