All of my tasks are skipping over and not including this date (yesterday) in their calculations. I do not have this set as a holiday in the main settings. Is there a holiday/day off setting for the specific sheet?
Hi Jennifer,
There is! If you right-click any column header and select Edit Project Settings, then select Dependency Settings. Click the Edit button under Working Days and edit holidays here.
If you don't have holidays in the sheet, then you may have formulas that have holidays in their calculations. More info on different date functions can be found in our help center: https://help.smartsheet.com/functions
A few date functions that come to mine which allow you to include holidays are NETWORKDAY, NETWORKDAYS, and WORKDAY.
Shaine - thank you, thank you. There was an incorrect holiday in there. It fixed it. I love this forum!
Glad to help!
We had a licensed user delete several files before leaving our organization. All of the sheets he owned have been transferred to someone else. However, there was one form we could not retrieve - Themed/Research Session Submission Form. Is there a way to recover that form? Any help is appreciated. Beverly Vance AMATYC…
Is there a way to save as a backup all sheets and workspaces? I am able to create a backup for all of the files shared with me. As the account's admin, can I back up all of the sheets and workspaces by all of our licensed users - even if they are not shared with me. We recently had a licensed use delete sheets and…
Hello all, I have a weekly report that I'm building and would like to be able to only expose two weeks worth of status. The report has a status and a commit date column and I'd like to remove anything that is "Done" and more than 2 weeks old. I'm trying to avoid having a report that has 100 rows of tasks that have been…