Sign in to join the conversation:
All of my tasks are skipping over and not including this date (yesterday) in their calculations. I do not have this set as a holiday in the main settings. Is there a holiday/day off setting for the specific sheet?
Hi Jennifer,
There is! If you right-click any column header and select Edit Project Settings, then select Dependency Settings. Click the Edit button under Working Days and edit holidays here.
If you don't have holidays in the sheet, then you may have formulas that have holidays in their calculations. More info on different date functions can be found in our help center: https://help.smartsheet.com/functions
A few date functions that come to mine which allow you to include holidays are NETWORKDAY, NETWORKDAYS, and WORKDAY.
Shaine - thank you, thank you. There was an incorrect holiday in there. It fixed it. I love this forum!
Glad to help!
I'm using a sheet for a project plan. I have a % Complete column and a manual dropdown column for Status (options are Not Started, In Progress, Completed, At Risk, etc.). I want to change the Status column to "Complete" when the % Complete for a task is changed to 100%. Screenshot of my automation set-up is below. Can…
Hi, I have a large project plan, and sometimes I get lost among all the information when trying to locate specific tasks in the Gantt chart. Does Smartsheet have a feature similar to Microsoft Project that allows you to quickly scroll to or find a task?
We have multiple projects for 150+ countries and we want to create a heatmap style grid to track which project is live in which country. Ideally, we want to convert this grid into a timeline, what would be the ideal way to create this smartsheet?