Hi There-
I am typing in the formula per the attached screenshot correctly, however it is returning the sum of 0. Any ideas?
Thanks-
Jim
Try Countif. Sumif works if you are summing columns of numbers, what you are trying to do is count how many times teh 0001-Aparell Accessories appears.
=Countif(Pyramid:Pyramid, "0001 - Apparel Accessories")
For sumif, you also have to add the column to add up together.
Jim, I think you have to use the =countif function.
Thanks! It worked perfectly!
Glad I could be of help. I keep this post on tap for whenever I need it!
https://help.smartsheet.com/functions
I have build a email validation in my sheet where entered emails from a form are entered in a contact field. another field verify the address and validades using the following formula: =IF(FIND("@xxxxxxx.com", [Student eMail]@row) = 0, 0, 1) if the checkbox is triggered (=0), then the registration is valid, and the the…
I have a sheet that has a good number of automations that populate a field based on a value changing in a cell. These same automations have been working just fine since March up until today. All of a sudden they are being triggered when there is no change to the cells in question. If I click into the cell history, it…
Hi, I'm in the midst of a Smartsheet trial and would like to understand how to set up a project schedule that uses a firm delivery deadline. I understand I could use Start-to-Finish relationships, but this disallows use of many to one predecessor relationships (multiple tasks that are gated by a single work item). I would…